MBTA November Service Changes - Representative Joe McGonagle

MBTA November Service Changes

The MBTA announced major construction work will continue in November to upgrade and enhance the subway and Commuter Rail system. With the goal of improving reliability and the accessibility of the T for all riders, MBTA crews will make advancements on critical Green Line central tunnel signal modernization, accessibility upgrades on the Green Line, and Commuter Rail improvements. The MBTA will also support MassDOT work as part of the West Roxbury Parkway Bridge Replacement project. More information on each project is below. 

In order to accomplish these system upgrades, service changes will take place in November on the Green, Franklin/Foxboro, Framingham/Worcester, Needham, Greenbush, Kingston, and Stoughton lines.   

Riders can find more information on service changes through in-station signage, in-station public announcements, and at mbta.com/PlannedWork. Transit Ambassadors and MBTA staff will be available on-site to offer information and assistance during these service changes. Riders are encouraged to subscribe to T-Alerts or to follow the MBTA on X @MBTA, @MBTA_CR, and @MBTA_CR_Alerts for up-to-date service information. 

On the Green Line 

As previously announced, Symphony Station remains closed to advance major accessibility upgrades at the station. The 85-year-old Symphony Station is being upgraded into a safer, fully accessible station featuring four new elevators and many other station enhancements. 

In November, work will continue as part of the Green Line C Branch Accessibility Improvements project. The MBTA is advancing critical accessibility improvements at seven above-ground stations on the C Branch, which will provide a faster and more comfortable boarding experience for all riders. 

The MBTA will also continue work on critical signal upgrades within the central Green Line tunnel. At over 100 years old, the MBTA’s Green Line signal system is being replaced with upgraded, modern technology. When the project is complete, the new signal system will provide the MBTA Operations team with improved train detection, better management of train congestion within the tunnel, and more consistent train spacing, which provides the foundation for improved service frequency. These operational improvements mean more reliable service for riders with fewer unplanned disruptions and emergency repairs caused by the older, aging signal system. Compatible with the upcoming fleet of new Type 10 Green Line cars, these signal upgrades also help prepare the MBTA for future generations of riders. 

To accomplish this work, the following service changes will take place: 
  

  • Green Line C branch service will bypass the following street-level stops during the following dates: 

o   Green Line trains will not stop at Saint Paul Street in the outbound direction through November 7. 
  

§  Trains will bypass the stop in the outbound direction during this time period. Riders can instead board or disembark one stop away at either Saint Mary’s Stret or Kent Street, which are 0.2 miles away (or about a 4- to 6-minute walk). 

 

o   Green Line trains will not stop at Hawes Street in the outbound direction through November 7.   

 

§  Trains will bypass the stop in the outbound direction during this time period. Riders can instead board or disembark one stop away at either Saint Mary’s Street or Kent Street, which are 0.2-0.3 miles away (or about a 4- to 6-minute walk). 

 

o   Green Line trains will not stop at Hawes Street in the inbound direction for 25 days, November 16 – December 10. 

 

§  Trains will bypass the stop in the inbound direction during this time period. Riders can instead board or disembark one stop away at either Saint Mary’s Street or Kent Street, which are 0.2-0.3 miles away (or about a 4- to 6-minute walk). 

 

o   Green Line trains will not stop at Summit Avenue in the inbound direction for 25 days, November 16 – December 10. 

 

§  Trains will bypass the stop in the inbound direction during this time period. Riders can instead board or disembark one stop away at either Coolidge Corner or Brandon Hall, which are 0.2 miles away (or about a 4- to 6-minute walk). 

 

  • As previously announced, Green Line service will be suspended between Government Center and Babcock Street on the B branch, Government Center and Kenmore on the C branch, North Station and Kenmore on the D branch, and Heath Street and North Station on the E Branch during the weekend of October 31 – November 1. 

 

 

·       Riders using shuttle bus service should budget ample extra travel time. For example, a rider travelling to Park Street from Boston College should budget at least an additional 25 minutes of travel in additional to their regular commute.  
  

·       B Branch: Free and accessible shuttle buses will operate between Babcock Street and Back Bay. 
 

·       Riders can connect to the Orange Line at Back Bay for continued service through downtown toward North Station.  
 

·       There will be free fares at Kenmore with the fare gates open. Fares will also be free at all surface-level stops west of Kenmore.  
 

·       Route 57 bus service will be fare-free during this service change.    
  

·       C Branch: Free and accessible shuttle buses will operate between Kenmore and Back Bay.      
  

·       Riders can connect to the Orange Line at Back Bay for continued service through downtown toward North Station.      
  

·       There will be free fares at Kenmore with the fare gates open. Fares will also be free at all surface-level stops west of Kenmore.    
  

·       D Branch: Free and accessible shuttle buses will operate between Kenmore and Back Bay.    
   

·       Riders can connect to the Orange Line at Back Bay for continued service through downtown toward North Station.      
  

·       There will be free fares at Kenmore and Riverside with the fare gates open. Fares will also be free at all surface-level stops west of Kenmore.    
  

·       E Branch: Route 39 will replace Green Line E Branch service between Heath Street and Back Bay. Extra buses will be added to the 39 to accommodate additional capacity. The route will be fare-free during this service change.   
  

·       The Framingham/Worcester Commuter Rail Line will be free between South Station and Lansdowne during these service changes. Passengers should note that regular fares are in place beyond Lansdowne. 
  

·       All shuttle buses are accessible to riders with disabilities. Some of the buses used will be lift-equipped, coach-style buses. Accessible van service will be available for Green Line stops between Kenmore and North Station for those who prefer it. Riders should see station personnel or use a station call box to request this service. 

 

  • Green Line service will be suspended between Government Center and Babcock Street on the B branch, Government Center and Cleveland Circle on the C branch, North Station and Kenmore on the D branch, and Heath Street and North Station on the E Branch for nine consecutive days, November 7 – 15. 

 

 

·       Riders using shuttle bus service should budget ample extra travel time. For example, a rider travelling to Park Street from Cleveland Circle should budget at least an additional 25 minutes of travel in additional to their regular commute.  
  

·       B Branch: Free and accessible shuttle buses will operate between Babcock Street and Back Bay.  
  

o   Riders can connect to the Orange Line at Back Bay for continued service through downtown toward North Station.  
  

o   Fares will not be collected at surface-level stops between Babcock Street and Boston College. 
  

o   Route 57 bus service will be fare-free during this service change.    
  

·       C Branch: Free and accessible shuttle buses will operate between Cleveland Circle and Back Bay.      
  

o   Riders can connect to the Orange Line at Back Bay for continued service through downtown toward North Station.  
  

o   Shuttle bus service will not be available at Saint Mary’s Street, Kent Street, or Brandon Hall in both directions. Riders should instead utilize shuttle bus service at the next nearest stop. 
  

·       D Branch: Free and accessible shuttle buses will operate between Kenmore and Back Bay.      
  

o   Riders can connect to the Orange Line at Back Bay for continued service through downtown toward North Station.  
  

o   There will be free fares at Kenmore and Riverside with the fare gates open. Fares will also be free at all surface-level stops west of Kenmore.    
  

·       E Branch: Route 39 will replace Green Line E Branch service between Heath Street and Back Bay. Extra buses will be added to the 39 to accommodate additional capacity. The route will be fare-free during this service change.    
  

·       All shuttle buses are accessible to riders with disabilities. However, some buses used during weekday periods will be lift-equipped, coach-style buses. All shuttle buses operating on weekends will be ramp-equipped, low-floor buses. Accessible van service will also be available between North Station and Kenmore, including Copley/Back Bay, for riders who prefer it. Riders should see station personnel or use a station call box to request accessible van service.   
  

·       The Worcester Commuter Rail Line will be fare-free between South Station, Back Bay, and Lansdowne during this Green Line service change. Riders should note that regular fares should be purchased beyond Lansdowne and regular fares should be purchased if traveling on a Commuter Rail line other than the Worcester Line.   

 

On the Franklin/Foxboro Commuter Rail Line 

Work will also take place in November to support the South Station Signal and Track Improvements Project. The MBTA is in the process of upgrading the Tower One track and signal system and the Cove track system to improve the reliability of service at South Station. This work will also support future growth of the MBTA and Amtrak. 

In order to accomplish this work, the following service change will take place:  

 

  • All Franklin/Foxboro Line trains will replaced with free and accessible shuttle buses between Foxboro and Walpole on November 6 and 13.   

 

On the Framingham/Worcester Commuter Rail Line 

 

In November, the MBTA will perform critical work on the Framingham/Worcester Line as part of Worcester Line track and signal improvements. The MBTA continues to invest in its Commuter Rail infrastructure to help keep service safe, reliable, and efficient. 

 

To accomplish this work, the following service suspension will take place: 

 

 

  • Framingham/Worcester Line service will be suspended between Framingham and South Station during the weekend of November 7 – 8.  
      

o   Free and accessible shuttle bus service will replace train service between Framingham and South Station. There will be four shuttle routes available during this closure.  
  

§  Shuttle Bus Route 1 will operate between Framingham, West Natick, Natick Center, Wellesley Square, Wellesley Hills, and South Station.    
  

§  Shuttle Bus Route 2 will operate between Wellesley Hills, Riverside for connections to the Green Line D branch, Auburndale, West Newton, Newtonville, Boston Landing, and South Station.    
  

§  Shuttle Bus Route 3 will operate between Framingham, West Natick, Natick Center, Wellesley Square, Wellesley Hills, and Back Bay.   
  

§  Shuttle Bus Route 4 will operate between Wellesley Hills, Riverside for connections to the Green Line D branch, Auburndale, West Newton, Newtonville, Boston Landing, and Back Bay.   
  

o   There will be no shuttle bus stops at Wellesley Farms and Lansdowne.       
  

§  Passengers who typically board at Wellesley Farms should instead travel to Wellesley Hills for alternate shuttle bus services.  
  

o   The Commuter Rail between Worcester and Framingham will be fare-free during this service change. 

 

On the Needham Commuter Rail Line 

MassDOT will perform work in November as part of the West Roxbury Parkway Bridge Replacement project, which will replace the bridge that carries the West Roxbury Parkway over the Needham Line. 

Work will also take place in November to support the South Station Signal and Track Improvements Project. The MBTA is in the process of upgrading the Tower One track and signal system and the Cove track system to improve the reliability of service at South Station. This work will also support future growth of the MBTA and Amtrak. 

To accomplish this work, the following service change will take place: 

  • Needham Line service will be suspended between Needham Heights and South Station beginning at approximately 11 PM through the end of service on November 6 and continuing through the weekend of November 7 – 8. 

o   There will be no shuttle bus service alternatives for this service change.    
  

o   Passengers may use Bus Routes 35, 36, and 37 between West Roxbury and Forest Hills for connections to Orange Line subway service between Forest Hills and Back Bay.    
  

o   Passengers may use Bus Route 59 between Needham Junction and Newton Highlands. Additional buses will operate on the 59 later into the evenings during these weekend dates to mimic the span of time Needham Line train service operates.    
  

o   There will be no service at Hersey.  
  

o   Riders using Bus Routes 35, 36, 37, or 59 should budget extra travel time. For example, a rider traveling to South Station from West Roxbury should budget at least 35 minutes of travel in addition to their regular trip time. 
  

  • There will be no Needham Line service between Forest Hills and South Station on November 6 and 13. Passengers should instead use the Orange Line subway for service to Forest Hills, Ruggles, and Back Bay, and for connections to the Red Line to South Station.  

On the Greenbush, Kingston, and Stoughton Commuter Rail Lines  

Work will take place in October to support the South Station Signal and Track Improvements Project. The MBTA is in the process of upgrading the Tower One track and signal system and the Cove track system to improve the reliability of service at South Station. This work will also support future growth of the MBTA and Amtrak. 

  • There will be no Greenbush or Kingston Line service between South Station and Braintree on November 6 and 13. Passengers should instead use the Red Line subway for service between South Station and Braintree, as well as the New Bedford/Fall River Line.   
  • There will be no Stoughton Line service between Canton Junction and South Station on November 6 and 13. Stoughton Line service will operate as a shuttle train between Canton Junction and Stoughton. Passengers will need to change at Canton Junction for Providence Line service to Boston. 

The MBTA previously announced service changes in November. More information is available here.  

Significance of Multi-Day Outages 

The MBTA is reminding riders that service outages such as these are a critical and necessary part of maintaining the infrastructure improvements that took place as part of the 2024 Track Improvement Program while also making further system upgrades and modernizing the MBTA’s infrastructure. This work cannot be performed during the overnight hours when the MBTA does not operate, and would be extremely inefficient and costly if planned during single weekend outages.  

Closing a section of the transit system for multiple days is the most efficient way to perform the MBTA’s routine maintenance, revitalization efforts, inspections, and upgrade work, and combines the efforts of multiple contractors and the MBTA workforce around the clock 24/7 to maximize productivity. This work is necessary and continuous to maintain the reliable service riders count on. 

Showing 1 reaction

Please check your e-mail for a link to activate your account.
  • Narlie Monteiro
    published this page in Events & Updates 2026-10-21 10:38:40 -0400
Volunteer